Orlando Health “D” Parking Expansion

Orlando, Florida

Being familiar with FINFROCK’s work on other garages on their campus, Orlando Health was confident that FINFROCK could meet its very aggressive schedule for this expansion project.

Capacity

918 stalls, 6 elevated levels

Owner

Orlando Health

Status

Completed 2006

FINFROCK was able to complete this project, which included demolition, site work, erection, and completion of the building, within six months. With only four weeks remaining in the schedule once erection was complete, FINFROCK was able to finish the retention pond, storm structures, landscape, irrigation and building finishes in order to acquire the certificate of occupancy by the contracted completion date.

 

FINFROCK served as architect of record, structural engineer, parking consultant, and design-build contractor for this garage expansion for Orlando Health.